journal article·2015-06

Construction schedule risk analysis of high roller-compacted concrete dams based on improved CSRAM

DengHua Zhong, ShiRui Yang, HaoTian Chang, Jia Yu, FuGen Yan

Publisher page

Abstract

The applied technology of high roller-compacted concrete (RCC) dams is quite complicated because of various risk factors, including the weather condition, supply of concrete aggregate, efficiency of transport machinery and dam surface machinery, and so on. In order to ensure the comprehensiveness, accuracy and objectivity of construction schedule risk analysis, a mathematical model called improved correlated schedule risk analysis model (CSRAM) is proposed in this paper. This model takes into account not only the construction features of high RCC dams, but also the stochastic variations of risk factors with the construction schedule, as well as their comprehensive effects. Using Monte Carlo method to solve this model enables the completion probability of a high RCC dam construction within plan time, and uncertainty analysis of risk factors. Compared with the conventional CSRAM, the improved CSRAM has higher completion probability and more convergent distribution of a simulation period, making analysis results more accurate and closer to actual engineering conditions. Among the ten risk factors selected, efficiency of dam surface machinery and proficiency of workers are found to be of the maximum uncertainty.
Source: openaire · Quality: candidate unverified · Source record ↗

Research context

OpenAlex topics: Dam Engineering and Safety · Construction Project Management and Performance · Geotechnical Engineering and Analysis

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

References (21)

Show source-provided references
1. Wu X. Fast construction method of RCCD in Longtan station. J Hydr Eng, 2007: 25–29
2. Bowman R A. Efficient sensitivity analysis of PERT network performance measures to significant changes in activity time parameters. J Oper Res Soc, 2007, 58: 1354–136010.1057/palgrave.jors.2602297 ↗
3. Dho H J, Khaled E. Fast and accurate risk evaluation for scheduling large-scale construction projects. J Comput Civil Eng, 2011, 25: 407–41710.1061/(ASCE)CP.1943-5487.0000106 ↗
4. Wang Z F, Ding J Y, Liu Y. Analysis of critical path and most critical activity in PERT networks based on Monte Carlo method. J Syst Eng Electron, 2012, 34: 1646–1651
5. Zhong D H, Liu K J, Yang X G. Uncertainty analysis for construction scheduling with flexible network simulation. Syst Eng-theory Pract, 2005, 2: 107–112
6. Young H K, Lisa I. Exploring Monte Carlo simulation applications for project management. Risk Manage, 2007: 44–57
7. Liu J Y. Correlation analysis of scheduling risks based on BN-CPM. J Hydro Eng, 2011, 30: 199–203
8. Liu J Y, Steven D. Analysis of correlation between engineering activities based on BN-CPM. J Hydr Eng, 2012, 31: 302–308
9. Okmen O, Oztasn A. Construction project network evaluation with correlated schedule risk analysis model. J Constr Eng Manage, 2008, 134: 49–6310.1061/(ASCE)0733-9364(2008)134:1(49) ↗
10. Xue L. Study on Schedule Risk Management in Construction Project. Beijing: Beijing Jiaotong University, 2012. 27–30
11. Zhong D H, Cai S K, Li Y Q. Risk analysis of hydropower project based on analytic network process and its application. J Hydro Eng, 2008, 27: 11–17
12. Wu Z R, Su H Z, Guo H Q. Risk assessment method of major unsafe hydroelectric project. Sci China Tech Sci, 2008, 51: 1345–135210.1007/s11431-008-0103-z ↗
13. Ba Y T. The Research on Project Risk Analysis Based on PERT. Dalian: Dalian University of Technology, 2010. 45–48
14. Van T L, Soo-Yong K, Nguyen V T. Quantifying schedule risk in construction projects using Bayesian belief networks using Bayesian belief networks. Int J Project Manage, 2009, 27: 39–5010.1016/j.ijproman.2008.03.003 ↗
15. Wu Z R, Su H Z, Guo H Q. Assessment model of dam operation risk based on monitoring data. Sci China Tech Sci, 2007, 50: 144–152
16. Su H Z, Wen Z P, Hu J, et al. Evaluation model for service life of dam based on time-varying risk probability. Sci China Tech Sci, 2009, 52: 1966–197310.1007/s11431-009-0151-z ↗
17. He X F, Gu C S, Wu Z R, et al. Dam risk assistant analysis system design. Sci China Tech Sci, 2008, 51: 101–10910.1007/s11431-008-6006-1 ↗
18. Chen S S, Zhong Q M, Cao W. Breach mechanism and numerical simulation for seepage failure of earth-rock dams. Sci China Tech Sci, 2012, 55: 1757–1764.10.1007/s11431-012-4768-y ↗
19. Bai Y C, Ji Z Q, Xu H J. Stability and self-adaption character of turbulence coherent structure in narrow-deep river bend. Sci China Tech Sci, 2012, 55: 2990–299910.1007/s11431-012-4977-4 ↗
20. Xu B S, Liu B B, Zheng D J, et al. Analysis method of thermal dam deformation. Sci China Tech Sci, 2012, 55: 1765–177210.1007/s11431-012-4839-0 ↗
21. Zhong D H, Chang H T, Li M C. Dynamic simulation of high RCC dam construction. Int J Hydropower Dams, 2012, 19: 70–74