Print time vs. elapsed time: A temporal analysis of a continuous printing operation for additive constructed concrete
Source abstract
Abstract
Abstract In additive construction, ambitious goals to fabricate a concrete building in less than 24 h are attempted. In the field, this goal relies on a metric of print time to make this conclusion, which excludes rest time and delays. The task to complete a building in 24 h was put to the test with the first attempt at a fully continuous print of a structurally reinforced additively constructed concrete (ACC) building. A time series analysis was performed on the events during the construction of a 512 ft2 (16 ft x 32 ft x 9.25 ft) building to explore the effect of delays on the completion time. This analysis included a study of the variation in comprehensive layer print times, expected trends and forecasting for what is expected in future prints of similar types. Furthermore, the study included a determination and comparison of print time, elapsed time and construction time, as well as a look at the effect of environmental conditions on the delay events. Upon finishing, the analysis concluded that the 3D printed building was completed in 14-hours of print time, 31.2-hours elapsed time, or a total of 5 days of construction time. This emphasizes that reports on newly 3D printed constructions need to provide a definition of time that includes all possible duration periods to communicate realistic capabilities of this new technology.
Source: openaire · Quality: candidate unverified · Source record ↗
Research context
OpenAlex topics: Innovations in Concrete and Construction Materials · Additive Manufacturing and 3D Printing Technologies · BIM and Construction Integration
SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.
References (36)
Show source-provided references
1. Development of the construction processes for reinforced additively constructed concrete
2. Randolph · 2017
3. Mix design and fresh properties for high-performance printing concrete10.1617/s11527-012-9828-z ↗
4. 3D printing of reinforced concrete elements: technology and design approach10.1016/j.conbuildmat.2018.01.018 ↗
5. Mechanical performance of wall structures in 3D printing processes: theory, design tools and experiments10.1016/j.ijmecsci.2018.01.010 ↗
6. Early age mechanical behaviour of 3D printed concrete: numerical modelling and experimental testing10.1016/j.cemconres.2018.02.001 ↗
7. Structural built-up of cement-based materials used for 3D-printing extrusion techniques10.1617/s11527-015-0571-0 ↗
8. Digital concrete: opportunities and challenges10.21809/rilemtechlett.2016.16 ↗
9. Large-scale 3D printing by a team of mobile robots
10. The rheology of fresh cement and concrete-a review
11. Investigation of the rheology and strength of geopolymer mixtures for extrusion-based 3D printing10.1016/j.cemconcomp.2018.10.002 ↗
12. Measurement of the rheological properties of high performance concrete: state of the art report10.6028/jres.104.028 ↗
13. Kosmatka · 2016 · 2016
14. Investigation of concrete mixtures for additive construction10.1108/RPJ-09-2015-0124 ↗
15. Gregurić · 2018
16. 3D printing using concrete extrusion: a roadmap for research10.1016/j.cemconres.2018.05.006 ↗
17. Hoffman · 2017
18. YRYS · 2017
19. Dome · 2018
20. 3D printing trends in building and construction industry: a review10.1080/17452759.2017.1326724 ↗
21. The benefits of 3D printing from concrete - concrete renovations
22. 3D concrete printing could free the world from boring buildings | The Independent
23. Mirani · 2013
24. Diggs · 2017
25. G. Al-Chaar, M. Case, G. Northrup, M. Kreiger, B. MacAllisterand W. Wagner, “Printable Concrete Composition,” US20180057405, 2018.
26. G. Al-Chaar, M. Case, G. Northrup, M. Kreiger, B. MacAllisterand W. Wagner, “US20180057405.pdf,” 2018.
27. Mix design and fresh properties for high-performance printing concrete10.1617/s11527-012-9828-z ↗
28. Effect of fly ash and silica fume on compressive strength of self-compacting concrete under different curing conditions10.1016/j.asej.2011.06.001 ↗
29. Rheological requirements for printable concretes10.1016/j.cemconres.2018.04.005 ↗
30. This $10,000 3d-printed concrete house took only 24 hours to build
31. J. D · 2018
32. Li · 2018
33. Emrath · 2012 · 1
34. Harvey · 1990
35. Box · 2015 · 37 · 709
36. Hyndman · 2018