Resilient Scheduling as a Response to Uncertainty in Construction Projects

Martina Milat, Snježana Knezić, Jelena Sedlar

Applied Sciences· Volume 11· Issue 14

Abstract

Complex construction projects are developed in a dynamic environment, where uncertainty conditions have a great potential to affect project deliverables. In an attempt to efficiently deal with the negative impacts of uncertainty, resilient baseline schedules are produced to improve the probability of reaching project goals, such as respecting the due date and reaching the expected profit. Prior to introducing the resilient scheduling procedure, a taxonomy model was built to account for uncertainty sources in construction projects. Thence, a multi-objective optimization model is presented to manage the impact of uncertainty. This approach can be described as a complex trade-off analysis between three important features of a construction project: duration, stability, and profit. The result of the suggested procedure is presented in a form of a resilient baseline schedule, so the ability of a schedule to absorb uncertain perturbations is improved. The proposed optimization problem is illustrated on the example project network, along which the probabilistic simulation method was used to validate the results of the scheduling process in uncertain conditions. The proposed resilient scheduling approach leads to more accurate forecasting, so the project planning calculations are accepted with increased confidence levels.
Source: crossref · Quality: baseline

Research context

OpenAlex topics: BIM and Construction Integration · Construction Project Management and Performance · Resource-Constrained Project Scheduling

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

Faculty of Civil Engineering, Architecture and Geodesy, University of Split, 21000 Split, Croatia

References (70)

Show source-provided references
1. Scientometric review of construction project schedule studies: Trends, gaps and potential research areas10.3846/jcem.2020.12317 ↗
2. Automation in construction scheduling: A review of the literature10.1007/s00170-015-7339-0 ↗
3. Cost optimization of project schedules under constrained resources and alternative production processes by mixed-integer nonlinear programming10.1108/ECAM-01-2019-0013 ↗
4. Multipurpose linear programming optimization model for repetitive activities scheduling in construction projects10.1016/j.autcon.2019.03.020 ↗
5. Mixed-Integer Linear Programming Approach for Scheduling Repetitive Projects with Time-Cost Trade-Off Consideration10.1061/(ASCE)CP.1943-5487.0000641 ↗
6. Mixed-Integer Nonlinear Programming Model for Nonlinear Discrete Optimization of Project Schedules under Restricted Costs10.1061/(ASCE)CO.1943-7862.0001074 ↗
7. Heuristic algorithm for ready-mixed concrete plant scheduling with multiple mixers10.1016/j.autcon.2017.08.013 ↗
8. Critical Sequence Crashing Heuristic for Resource-Constrained Discrete Time–Cost Trade-Off Problem10.1061/(ASCE)CO.1943-7862.0001077 ↗
9. Scheduling Policies for the Stochastic Resource Leveling Problem10.1061/(ASCE)CO.1943-7862.0000936 ↗
10. Multi-objective symbiotic organisms optimization for making time-cost tradeoffs in repetitive project scheduling problem10.3846/jcem.2019.9681 ↗
11. Utility of Genetic Algorithms for Solving Large-Scale Construction Time-Cost Trade-Off Problems10.1061/(ASCE)CP.1943-5487.0000718 ↗
12. Pareto Front Particle Swarm Optimizer for Discrete Time-Cost Trade-Off Problem10.1061/(ASCE)CP.1943-5487.0000606 ↗
13. Profit optimization for multi-mode repetitive construction project with cash flows using metaheuristics10.1007/s43452-021-00218-2 ↗
14. Construction project scheduling under workspace interference10.1111/mice.12547 ↗
15. Automated Methods and Systems for Construction Planning and Scheduling: Critical Review of Three Decades of Research10.1061/(ASCE)CO.1943-7862.0002093 ↗
16. ElMenshawy, M., and Marzouk, M. (2021). Automated BIM schedule generation approach for solving time–cost trade-off problems. Eng. Constr. Archit. Manag., Epub ahead of printing.10.1108/ECAM-08-2020-0652 ↗
17. BIM-based draft schedule generation in reinforced concrete-framed buildings10.1108/CI-11-2018-0094 ↗
18. BIM-Based Combination of Takt Time and Discrete Event Simulation for Implementing Just in Time in Construction Scheduling under Constraints10.1061/(ASCE)CO.1943-7862.0001940 ↗
19. Dasović, B., Galić, M., and Klanšek, U. (2020). A Survey on Integration of Optimization and Project Management Tools for Sustainable Construction Scheduling. Sustainability, 12.10.3390/su12083405 ↗
20. Nusen, P., Boonyung, W., Nusen, S., Panuwatwanich, K., Champrasert, P., and Kaewmoracharoen, M. (2021). Construction Planning and Scheduling of a Renovation Project Using BIM-Based Multi-Objective Genetic Algorithm. Appl. Sci., 11.10.3390/app11114716 ↗
21. Xie, L., Chen, Y., and Chang, R. (2021). Scheduling Optimization of Prefabricated Construction Projects by Genetic Algorithm. Appl. Sci., 11.10.3390/app11125531 ↗
22. Work package-based information modeling for resource-constrained scheduling of construction projects10.1016/j.autcon.2019.102958 ↗
23. Sbiti, M., Beddiar, K., Beladjine, D., Perrault, R., and Mazari, B. (2021). Toward BIM and LPS Data Integration for Lean Site Project Management: A State-of-the-Art Review and Recommendations. Buildings, 11.10.3390/buildings11050196 ↗
24. Defining uncertainty in projects—A new perspective10.1016/j.ijproman.2007.08.005 ↗
25. Project Management Institute (2016). Construction Extension to the PMBOK Guide, Project Management Institute, Inc.
26. Building information modeling as a risk transformer: An evolutionary insight into the project uncertainty10.1016/j.autcon.2018.03.032 ↗
27. BIM based risk management for design bid build (DBB) design process in the United Arab Emirates: A conceptual framework10.1007/s13198-020-00993-w ↗
28. Resilience analysis for project scheduling with renewable resource constraint and uncertain activity durations
29. A multi-objective optimization approach to project scheduling with resiliency criteria under uncertain activity duration10.1007/s10479-019-03375-z ↗
30. A new surrogate measure for resilient approach to construction scheduling10.1016/j.procs.2021.01.192 ↗
31. Zhao, M., Wang, X., Yu, J., Xue, L., and Yang, S. (2020). A construction schedule robustness measure based on improved prospect theory and the Copula-CRITIC method. Appl. Sci., 10.10.3390/app10062013 ↗
32. Zhao, M., Wang, X., Yu, J., Bi, L., Xiao, Y., and Zhang, J. (2020). Optimization of Construction Duration and Schedule Robustness Based on Hybrid Grey Wolf Optimizer with Sine Cosine Algorithm. Energies, 13.10.3390/en13010215 ↗
33. Chapman, C., and Ward, S. (2003). Project Risk Management: Processes, Techniques and Insights, John Wiley & Sons Ltd.. [2nd ed.].
34. Social semantic approach to support communication in AEC
35. Elghamrawy, T., Boukamp, F., and Kim, H.S. (2009, January 5–7). Ontology-based, semi-automatic framework for storing and retrieving on-site construction problem information—An RFID-based case study. Proceedings of the Construction Research Congress 2009: Building a Sustainable Future, Seattle, WA, USA.10.1061/41020(339)47 ↗
36. Knowledge-based approach to construction project risk management10.1061/(ASCE)0887-3801(2001)15:3(170) ↗
37. A study of ontology-based risk management framework of construction projects through project life cycle10.1016/j.autcon.2009.05.005 ↗
38. Construction risk knowledge management in BIM using ontology and semantic web technology10.1016/j.ssci.2016.04.008 ↗
39. Domain taxonomy for construction concepts: Toward a formal ontology for construction knowledge10.1061/(ASCE)0887-3801(2005)19:4(394) ↗
40. Facilitating knowledge sharing and reuse in building and construction domain: An ontology-based approach10.1007/s10845-013-0856-5 ↗
41. Developing taxonomy for the domain ontology of construction contractual semantics: A case study on the AIA A201 document10.1016/j.aei.2015.03.009 ↗
42. Ontology for relating risk and vulnerability to cost overrun in international projects10.1061/(ASCE)CP.1943-5487.0000090 ↗
43. Ontology-based partial building information model extraction10.1061/(ASCE)CP.1943-5487.0000277 ↗
44. Uncertainty processing and risk monitoring in construction projects using hierarchical probabilistic relational models10.1111/mice.12391 ↗
45. Jiang, S., Wang, N., and Wu, J. (2018). Combining BIM and ontology to facilitate intelligent green building evaluation. J. Comput. Civ. Eng., 32.10.1061/(ASCE)CP.1943-5487.0000786 ↗
46. Ontology for safety risk identification in metro construction10.1016/j.compind.2019.04.001 ↗
47. Ontology-based semantic modeling of knowledge in construction: Classification and identification of hazards implied in images10.1061/(ASCE)CO.1943-7862.0001767 ↗
48. Ontology-based framework for building environmental monitoring and compliance checking under BIM environment10.1016/j.buildenv.2018.05.046 ↗
49. Finance-Based Scheduling: Tool to Maximize Project Profit Using Improved Genetic Algorithms10.1061/(ASCE)0733-9364(2005)131:4(400) ↗
50. GA-based multi-objective optimization of finance-based construction project scheduling10.1007/s12205-010-0849-2 ↗
51. Finance-based scheduling multi-objective optimization: Benchmarking of evolutionary algorithms10.1016/j.autcon.2020.103392 ↗
52. SACRE: Supporting contextual requirements’ adaptation in modern self-adaptive systems in the presence of uncertainty at runtime10.1016/j.eswa.2018.01.009 ↗
53. A multi-agent model to manage risks in construction project (SMACC)10.1016/j.autcon.2015.06.005 ↗
54. Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey
55. Ustinovičius, L. (2007, January 16–18). Uncertainty analysis in construction project’s appraisal phase. Proceedings of the 9th International Conference Modern Building Materials, Structures and Techniques, Vilnius, Lithuania.
56. Ali, Z., Zhu, F., and Hussain, S. (2018). Identification and assessment of uncertainty factors that influence the transaction cost in public sector construction projects in Pakistan. Buildings, 8.10.3390/buildings8110157 ↗
57. Sacco, G., and Tzitzikas, Y. (2013). Dynamic Taxonomies and Faceted Search, Springer.
58. Ranganathan, S.R. (1965). The Colon Classification, Rutgers University Press.
59. Global Perception of Sustainable Construction Project Risks10.1016/j.sbspro.2014.03.051 ↗
60. Identification and classification of uncertainties in the application of environmental models10.1016/j.envsoft.2010.04.011 ↗
61. Robust scheduling and robustness measures for the discrete time/cost trade-off problem10.1016/j.ejor.2010.05.046 ↗
62. Investigation of surrogate measures of robustness for project scheduling problems10.1016/j.cie.2019.01.041 ↗
63. Profit Measures for Construction Projects10.1061/(ASCE)0733-9364(1986)112:2(273) ↗
64. Ahuja, H. (1976). Construction Performance Control by Networks, Wiley.
65. A max-min ant system for the finance-based scheduling problem10.1016/j.cie.2017.06.016 ↗
66. Hendrickson, C. (2021, May 18). Project Management for Construction: Fundamental Concepts for Owners, Engineers, Architects and Builders. Available online: https://www.cmu.edu/cee/projects/PMbook/.
67. Demeulemeester, E., and Herroelen, W. (2002). Project Scheduling, Kluwer Academic Publishers.
68. Interactive analysis of multiple-criteria project scheduling problems10.1016/S0377-2217(97)00336-6 ↗
69. Chaturvedi, S., Rajasekar, E., and Natarajan, S. (2020). Multi-objective Building Design Optimization under Operational Uncertainties Using the NSGA II Algorithm. Buildings, 10.10.3390/buildings10050088 ↗
70. On simulation in planning networks10.1080/02630259208970639 ↗