Construction Project Cost Prediction Method Based on Improved BiLSTM

Chaoxue Wang, Jiale Qiao

Applied Sciences· Volume 14· Issue 3

Abstract

In construction project management, accurate cost forecasting is critical for ensuring informed decision making. In this article, a construction cost prediction method based on an improved bidirectional long- and short-term memory (BiLSTM) network is proposed to address the high interactivity among construction cost data and difficulty in feature extraction. Firstly, the correlation between cost-influencing factors and the unilateral cost is calculated via grey correlation analysis to select the characteristic index. Secondly, a BiLSTM network is used to capture the temporal interactions in the cost data at a deep level, and the hybrid attention mechanism is incorporated to enhance the model’s feature extraction capability to comprehensively capture the interactions among the features in the cost data. Finally, a hyperparameter optimisation method based on the improved particle swarm optimisation algorithm is proposed using the prediction accuracy as the fitness function of the algorithm. The MAE, RMSE, MPE, MAPE, and coefficient of determination of the simulated prediction results of the proposed method on the dataset are 7.487, 8.936, 0.236, 0.393, and 0.996%, respectively, where MPE is a positive coefficient. This avoids the serious consequences of underestimating the cost. Compared with the unimproved BiLSTM, the MAE, RMSE, and MAPE are reduced by 15.271, 18.193, and 0.784%, respectively, which reflects the superiority and effectiveness of the method and can provide technical support for project cost estimation in the construction field.
Source: crossref · Quality: baseline

Research context

OpenAlex topics: Infrastructure Maintenance and Monitoring · BIM and Construction Integration

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

School of Information and Control Engineering, Xi’an University of Architecture and Technology, Xi’an 710055, China

Funding

the National Natural Science Foundation of China · the Natural Science Foundation of Shaanxi Province

References (35)

Show source-provided references
1. Predicting City-Level Construction Cost Index Using Linear Forecasting Models10.1061/(ASCE)CO.1943-7862.0001973 ↗
2. Improving Accuracy in Predicting City-Level Construction Cost Indices by Combining Linear Arima and Nonlinear ANNs10.1061/(ASCE)ME.1943-5479.0001008 ↗
3. Construction Costs Forecasting: Comparison of the Accuracy of Linear Regression and Support Vector Machine Models
4. Developing an Integrative Data Intelligence Model for Construction Cost Estimation10.1155/2022/4285328 ↗
5. Dynamic Cost Estimation of Reconstruction Project Based on Particle Swarm Optimization Algorithm10.31449/inf.v47i2.4026 ↗
6. Forecasting Construction Project Cost Based on BP Neural Network
7. An Algorithm for Construction Project Cost Forecast Based on Particle Swarm Optimization-guided BP Neural Network
8. Discussion on the Prediction of Engineering Cost Based on Improved BP Neural Network Algorithm10.3233/JIFS-179193 ↗
9. Cost Index Predictions for Construction Engineering Based on LSTM Neural Networks10.1155/2020/6518147 ↗
10. Predicting the Volatility of Highway Construction Cost Index Using Long Short-Term Memory10.1061/(ASCE)ME.1943-5479.0000784 ↗
11. Near Real-Time Wind Speed Forecast Model with Bidirectional LSTM Networks10.1016/j.renene.2022.12.123 ↗
12. Dynamic and Explainable Deep Learning-Based Risk Prediction on Adjacent Buildings Induced by Deep Excavation10.1016/j.tust.2023.105243 ↗
13. A Deep Bi-directional Long-Short Term Memory Neural Network-Based Methodology to Enhance Short-Term Electricity Load Forecasting for Residential Applications10.1016/j.cie.2022.108364 ↗
14. Point and Interval Forecasting of Ultra-short-Term Wind Power Based on a Data-Driven Method and Hybrid Deep Learning Model10.1016/j.energy.2022.124384 ↗
15. The Performance of LSTM and BiLSTM in Forecasting Time Series
16. Ensemble Approach Based on Bagging, Boosting and Stacking for Short-Term Prediction in Agribusiness Time Series10.1016/j.asoc.2019.105837 ↗
17. A Watershed Water Quality Prediction Model Based on Attention Mechanism and Bi-LSTM10.1007/s11356-022-21115-y ↗
18. A Time-Varying Stock Portfolio Selection Model Based on Optimised PSO-BiLSTM and Multi-objective Mathematical Programming Under Budget Constraints10.1007/s00521-023-08669-9 ↗
19. Factors Affecting the Accuracy of Cost Estimate: Case of Jordan10.1108/ECAM-10-2016-0232 ↗
20. A Water Quality Assessment Method Based on an Improved Grey Relational Analysis and Particle Swarm Optimisation Multi-classification Support Vector Machine10.3389/fpls.2023.1099668 ↗
21. Performance Evaluation of Normalization-Based CBR Models for Improving Construction Cost Estimation10.1016/j.autcon.2020.103329 ↗
22. Conceptual Estimation of Construction Costs Using the Multistep Ahead Approach10.1061/(ASCE)CO.1943-7862.0001150 ↗
23. Improving Robustness of Case-Based Reasoning for Early-Stage Construction Cost Estimation10.1016/j.autcon.2023.104777 ↗
24. Covariance Effect Analysis of Similarity Measurement Methods for Early Construction Cost Estimation Using Case-Based Reasoning10.1016/j.autcon.2017.04.009 ↗
25. Cost Estimation Model Using Modified Parameters for Construction Projects10.1155/2019/8290935 ↗
26. Influencing Factors and Prediction Model of Construction Project Duration
27. A General Survey on Attention Mechanisms in Deep Learning10.1109/TKDE.2021.3126456 ↗
28. A Review on the Attention Mechanism of Deep Learning10.1016/j.neucom.2021.03.091 ↗
29. Kingma, D.P., and Ba, J. (2014). Adam: A Method for Stochastic Optimization. arXiv.
30. Jain, M., Saihjpal, V., Singh, N., and Singh, S.B. (2022). An Overview of Variants and Advancements of PSO Algorithm. Appl. Sci., 12.10.3390/app12178392 ↗
31. Particle Swarm Optimization: A Comprehensive Survey10.1109/ACCESS.2022.3142859 ↗
32. A Theoretical Guideline for Designing an Effective Adaptive Particle Swarm10.1109/TEVC.2019.2906894 ↗
33. Zhao, G., Jiang, D., Liu, X., Tong, X., Sun, Y., Tao, B., Kong, J., Yun, J., Liu, Y., and Fang, Z. (2022). A Tandem Robotic Arm Inverse Kinematic Solution Based on an Improved Particle Swarm Algorithm. Front. Bioeng. Biotechnol., 10.10.3389/fbioe.2022.832829 ↗
34. A Hybrid Fault Diagnosis Methodology with Support Vector Machine and Improved Particle Swarm Optimization for Nuclear Power Plants10.1016/j.isatra.2019.05.016 ↗
35. Evaluation of Cloud Computing Resource Scheduling Based on Improved Optimization Algorithm10.1007/s40747-020-00163-2 ↗