Resource-Based Quality Performance Estimation Method for Construction Operations

Young-Jun Park, Chang-Yong Yi

Applied Sciences· Volume 11· Issue 9

Abstract

Construction quality is one of the primary management objectives relating to duration and cost for construction projects. Project managers struggle with minimizing duration and cost while maximizing quality for construction projects. In construction projects, duration and cost have management priorities. On the other hand, quality is considered a matter of achievement only when it reaches a certain level. Although the importance of quality control in construction management has been constantly discussed, it has still been sacrificed under the goal of shortening construction duration and reducing costs. This study presents a method for estimating the quantitative quality performance of construction operations in which the level of detail is breaking into the work task level for intuitive quality performance evaluation. For this purpose, quality weights of resources that have a proportional quality importance weight and quality performance indexes of resources are utilized for estimating the quantitative quality performance of construction operations. Quality performance estimation and the resource allocation optimization system is presented and validated using a construction simulation model.
Source: crossref · Quality: baseline

Research context

OpenAlex topics: BIM and Construction Integration · Construction Project Management and Performance · Risk and Safety Analysis

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

Intelligent Construction Automation Center, Kyungpook National University, Daegu 41566, Korea

Funding

This research was supported by Kyungpook National University Development Project Research Fund, 2018

References (42)

Show source-provided references
1. Hancher, D. (2002). Construction planning and scheduling. Assoc. Gen. Contract. Am., 1.10.1201/9781420041217.ch2 ↗
2. Total systems intervention: An integrated approach to time, cost and quality management10.1080/01446199500000027 ↗
3. Rad, H.N., and Khosrowshahi, F. (1998, January 9–11). Quality measurement in construction projects. Proceedings of the Association of Researchers in Construction Management, Reading, UK.
4. Total quality management for construction10.1061/(ASCE)0733-9364(1985)111:2(117) ↗
5. Critical factors affecting quality performance in construction projects10.1080/14783360600750444 ↗
6. Barriers and benefits of quality management in the construction industry: An empirical study10.1080/14783363.2010.487673 ↗
7. Improving the materials supply system in small-sized building firms10.1016/S0926-5805(98)00112-5 ↗
8. Stevens, J.D., Kloppenborg, T.J., and Glagola, C.R. (1994). Quality Performance Measurements of the EPC Process: The Blueprint, University of Texas at Austin.
9. Smith, G.R. (2001). Quality-Based Performance Rating of Contractors for Prequalification and Bidding Purposes (NCHRP-W38), Citeseer.
10. Anderson, S.D., and Russell, J.S. (2001). Guidelines for Warranty, Multi-Parameter, and Best Value Contracting, Transportation Research Board.
11. Time-cost-quality trade-off analysis for highway construction10.1061/(ASCE)0733-9364(2005)131:4(477) ↗
12. Optimizing multi-mode time-cost-quality trade-off of construction project using opposition multiple objective difference evolution
13. Multi-objective optimization of time-cost-quality in construction projects using genetic algorithm
14. Time–cost–quality trade-off analysis for planning construction projects10.1108/ECAM-12-2017-0271 ↗
15. Hu, W., and He, X. (2014). An innovative time-cost-quality tradeoff modeling of building construction project based on resource allocation. Sci. World J., 2014.10.1155/2014/673248 ↗
16. Multi-attribute decision -making methods for assessment of quality in bridges and road construction: State-of-the-art surveys10.3846/1822-427X.2008.3.152-160 ↗
17. Cyclone—Method for modeling job site processes10.1061/JCCEAZ.0000712 ↗
18. Integrated simulation system for construction operation and project scheduling10.1061/(ASCE)CP.1943-5487.0000061 ↗
19. Simulation approach to evaluating cost efficiency of selective demolition practices: Case of Hong Kong’s Kai Tak airport demolition10.1061/(ASCE)0733-9364(2009)135:6(448) ↗
20. Predictive tool for estimating accident risk10.1061/(ASCE)0733-9364(2003)129:4(431) ↗
21. Leapcon: Simulation of lean construction of high-rise apartment buildings10.1061/(ASCE)0733-9364(2007)133:7(529) ↗
22. Evaluating qualification-based selection system: A simulation approach10.1061/(ASCE)CO.1943-7862.0000013 ↗
23. Importance of operational efficiency to achieve energy efficiency and exhaust emission reduction of construction operations10.1061/(ASCE)CO.1943-7862.0000609 ↗
24. Stochastic carbon emission estimation method for construction operation10.3846/13923730.2014.992466 ↗
25. Halpin, D.W., and Martinez, L.H. (1999, January 5–8). Real world applications of construction process simulation. Proceedings of the Winter Simulation Conference Proceedings, Phoenix, AZ, USA.10.1145/324898.324947 ↗
26. Virtual shop model for experimental planning of steel fabrication projects10.1061/(ASCE)0887-3801(2006)20:5(308) ↗
27. Pang, H., Zhang, C., and Hammad, A. (2006, January 4). Sensitivity analysis of construction simulation using cell-devs and microcyclone. Proceedings of the Proceedings—Winter Simulation Conference, Monterrey, CA, USA.10.1109/WSC.2006.322989 ↗
28. Stochastic productivity assessment of continuous flight auger piles10.3763/asre.2008.0045 ↗
29. Exploring the environmental modeling of road construction operations using discrete-event simulation10.1016/j.autcon.2012.02.011 ↗
30. Productivity and CO2 emission analysis for tower crane utilization on high-rise building projects10.1016/j.autcon.2012.11.044 ↗
31. Factors affecting the quality of building projects in Hong Kong10.1108/02656710010298445 ↗
32. Corona-Suárez, G.A., Abourizk, S.M., and Karapetrovic, S. (2014). Simulation-based fuzzy logic approach to assessing the effect of project quality management on construction performance. J. Qual. Reliab. Eng., 2014.10.1155/2014/203427 ↗
33. Catapillar (2015). Caterpillar Performance Handbook, Catapillar Inc.
34. Halpin, D., and Riggs, L. (1994). PLanning and Analysis of Construction Operations, John Wiley & Sons.
35. Gupta, A. (2016). Simulation Modeling and Analysis, McGraw-Hill.10.1201/9781315183176-14 ↗
36. Mure, N., Scott, J., Seward, D., Quayle, S., Clayton, C., and Rust, M. (2002, January 23–25). Just-in-time continuous flight auger piles using an instrumented auger. Proceedings of the 19th International Symposium on Automation and Robotics in Construction (ISARC), Washington DC, USA.10.22260/ISARC2002/0071 ↗
37. Coduto, D.P., Kitch, W.A., and Yeung, M.R. (2001). Foundation Design: Principles and Practices, Prentice Hall.
38. Peurifoy, R.L., Schexnayder, C.J., Schmitt, R.L., and Shapira, A. (2018). Construction Planning, Equipment, and Methods, McGraw-Hill Education.
39. Productivity and cost assessment for continuous flight auger piles10.1061/(ASCE)0733-9364(2005)131:6(677) ↗
40. Research challenges of industry 4.0 for quality management10.1007/978-3-319-32799-0_10 ↗
41. Product decision-making information systems, real-time big data analytics, and deep learning-enabled smart process planning in sustainable industry 4.010.22381/JSME8320202 ↗
42. Networked, smart, and responsive devices in industry 4.0 manufacturing systems10.22381/EMFM15320203 ↗