journal article·2022-12-04Open access

Modelling the Stages of Pre-Project Preparation and Design Development in the Life-Cycle of an Investment and Construction Project

Azariy Lapidus, Dmitriy Topchiy, Tatyana Kuzmina, Polina Bolshakova

Applied Sciences· Volume 12· Issue 23

Abstract

The stages of pre-project preparation and design development are the fundamentals to the further implementation of an investment and construction project. The success of construction and commissioning of facilities depends on the smooth completion of these stages. The duration of stages depends on the competence and coordination of interaction between participants of an investment and construction project, rational decision making by the project manager and a number of other factors. Identifying these factors and finding rational planning options in terms of the stages of pre-project preparation and design development is a highly relevant task. With this in mind, the authors have developed an organizational and management model of a rational procedure to be implemented by the project manager at the stages of pre-project preparation and design development for a facility to be constructed. The model takes into account the influence of negative factors. The authors have also developed a method for selecting rational solutions at the stages in question. The analysis of the research literature and regulatory documents was performed for this purpose. The method of expert evaluations, elements of numerical analysis, mathematical processing of practical results and methods of mathematical modeling were applied. As a result, the authors have developed an organizational and management model for a rational combination of procedures at the stages of pre-project preparation and design development for a facility to be constructed and derived a formula determining the duration of implementation of each stage and a technique designated for selecting rational solutions at the stages in question. The findings of this study can simplify project planning and process management at the stages of pre-project preparation and design development in terms of information modeling.
Source: crossref · Quality: baseline

Research context

OpenAlex topics: Construction Management and Sustainability · Economic and Industrial Development · Engineering and Environmental Studies

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

Department of Technology and Organization of Construction Production, Moscow State University of Civil Engineering (National Research University) (MGSU), 26 Yaroslavskoe Shosse, 129337 Moscow, Russia

Funding

Moscow State University of Civil Engineering (National Research University) (MGSU)

References (46)

Show source-provided references
1. Completion of administrative procedures by the developer (technical customer)10.1051/e3sconf/202125809004 ↗
2. Changes in the organization of residential construction as a result of the introduction of a comprehensive list of administrative procedures
3. On some problems of the investment climate in the field of construction
4. Administrative procedures in the implementation of investment and construction projects: A management mechanism
5. Analysis of procedures for obtaining permits for construction
6. Information model of the life cycle of a construction project
7. Ginzburg, A.V. (2020, January 30). Technologies of information modeling of the life cycle of the object of capital construction. Proceedings of the Actual Problems of the Construction Industry and Education, First National Conference, Moscow, Russia.
8. BIM-technologies during the life cycle of the construction facility
9. Zelentsov, L.B., Kravchenko, A.I., and Pirko, D.V. (2020, January 19–31). The problems of organization and regulation of the relationship between participants of the investment and construction project. Proceedings of the Construction and Architecture, International Scientific and Practical Conference, Rostov-on-Don, Russia.
10. Zelentsov, L.B., Mailyan, L.D., and Shogenov, M.S. (2018). Management of temporal parameters in complex dynamic building systems. Eng. Her. Don., 2.
11. Dynamic methods of forecasting time and cost parameters of construction projects
12. Attracting investment to the regions through public-private partnerships: Problems, status, prospects
13. Communication problems causing governmental projects delay–Kuwait case study
14. Introducing an innovation promotion model for construction projects10.1108/ECAM-03-2020-0145 ↗
15. Optimization of environmental impacts of construction projects: A time–cost–quality trade-off approach10.1007/s13762-020-02838-2 ↗
16. Analysis of Factors Affecting Cost and Time Overruns in Construction Projects
17. Kuzmina, T.K., Bolshakova, P.V., Ledovskikh, L.I., and Zueva, D.D. (2020, January 30). Features of the work of the technical customer with the use of BIM-technologies. Proceedings of the Actual Problems of the Construction Industry and Education, First National Conference, Moscow, Russia.
18. Bennett, F.L. (2003). The Management of Construction: A Project Life Cycle Approach, Butterworth-Heinemann.
19. Clough, R.H., Sears, G.A., Sears, S.K., Rounds, J.L., and Segner, R.O. (2015). Construction Project Management: A Practical Guide to Field Construction Management, Wiley. [6th ed.].
20. COVID-19 certificate as a cutting-edge issue in changing the perception of restaurants’ visitors-Illustrations from Serbian urban centers10.3389/fpsyg.2022.914484 ↗
21. Factors affecting the timing of construction
22. Identification and systematization of factors in the preparation of facilities for construction by the technical customer (developer)
23. Research of influence of preparation of initial permissive documentation on terms of realization of investment-construction projects
24. The study of the existing system of development and implementation of investment and construction projects
25. Implementing large-scale construction projects through application of the systematic and integrated method10.1088/1757-899X/365/6/062002 ↗
26. Systemic integrated method for assessing factors affecting construction timelines
27. Development of an extended STIRPAT model to assess the driving factors of household carbon dioxide emissions in China10.1016/j.jenvman.2022.116502 ↗
28. Popescu, C.R.G. (2021). Measuring Progress towards Sustainable Development Goals: Creativity, Intellectual Capital and Innovation. Handbook of Research on Novel Practices and Current Successes in Achieving the Sustainable Development Goals, IGI Global. Chapter 6.10.4018/978-1-7998-8426-2.ch006 ↗
29. (2022, November 26). Measuring the Impacts of Business on Well-Being and Sustainability. Available online: https://www.oecd.org/fr/investissement/measuring-business-impacts-on-peoples-well-being.htm.
30. (2022, November 26). Toward Sustainable Economic Development through Promoting and Enabling Responsible Business Conduct. Available online: https://www.oecd-ilibrary.org/sites/f7813858-en/index.html?itemId=/content/component/f7813858-en.
31. Mubarak, S. (2010). Construction Project Scheduling and Control, John Wiley & Sons.10.1002/9780470912171 ↗
32. (2022, June 29). Federal Service State Statistics, Available online: https://rosstat.gov.ru/.
33. Strengthening the functions of financing, accounting and reporting in the activities of the services of the developer (customer) with the transition to market relations
34. Systematization of the major stages of the client in certain branches of construction production10.1051/matecconf/20168605012 ↗
35. Modelling the Reduction of Project Making Duration10.1051/matecconf/201711700129 ↗
36. Methods of Expert Evaluations10.21686/2500-3925-2015-1-183-187 ↗
37. Application of methods of expert evaluation in scientific research. The required number of experts
38. Combining the functions of the main participants of investment and construction activities at the present stage
39. Peculiarities of the life cycle and stages of development of an investment and construction project10.22227/1997-0935.2013.6.223-228 ↗
40. Oleynik, P.P. (2010). Organization of Construction Production, Scientific Publication, ASV.
41. Organization of planning of building production
42. Application of network planning in the design, preparation and construction of urban housing programs
43. Optimization of planning processes of design works and approval of design estimates for capital construction, reconstruction and re-profiling facilities
44. Facility Management and Its Importance in the Analysis of Building Life Cycle10.1016/S2212-5671(15)00814-X ↗
45. Peculiarities of the initial data collection for non-productive objects in the technical customer’s activity at the stage of pre-project preparation
46. Features of the organization and conduct of competitive bidding for the implementation of investment and construction projects