journal article·2022-03-30Open access

Time Connection of Subsequent Construction Processes Estimated by Statistical Method

Stanislav Smugala, Darja Kubečková

Applied Sciences· Volume 12· Issue 7

Abstract

An integral part of managing the construction of investment units is the monitoring of labor productivity using statistical methods in combination with construction software. Such a combination includes a number of methods and modeling, among which is a method for determining the probability of the completion of construction processes based on the recorded mean value of labor productivity and its variations. For investment units consisting of two or more objects, it is necessary to assess the probability of the completion of construction processes related to follow-up activities and which are carried out by the same work crews. Based on the selected probability modeling, the aim of this contribution was to show how statistical methods and software support can contribute to savings in resources, both human and time, in construction production. The aspect is documented in a case study of residential buildings. The Lindeberg–Lévy and Moivre–Laplace theory and the Bernoulli principle were used for mathematical modeling. The CONTEC construction software was applied as the software support. The performed modeling showed a decrease in the mean value of performance for all the processes examined compared to the planned values, except for the implementation of reinforced concrete monolithic structures. For these reasons, the working capacities had to be increased in order to meet construction milestones.
Source: crossref · Quality: baseline

Research context

OpenAlex topics: Construction Project Management and Performance · BIM and Construction Integration · Mechanical and Thermal Properties Analysis

SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.

Affiliations

Department of Construction, Faculty of Civil Engineering, VŠB-Technical University Ostrava, Ludvíka Podéště 1875/17, 708 33 Ostrava, Czech Republic

References (83)

Show source-provided references
1. Kelley, J., and Walker, M. (1959, January 1–3). Critical-Path Planning and Scheduling. Proceedings of the Eastern Joint Conference, Boston, MA, USA.10.1145/1460299.1460318 ↗
2. An Iterative Calculation Method and Its Scope of Application in Scheduling Construction Operations According to the BKN Unit Network Program
3. Jarský, Č. (2000). Automatizovaná Příprava a Řízení Realizace Staveb, CONTEC.
4. Newell, M., and Grashina, M. (2003). The Project Management Question and Answer Book, Amacom, American Management.
5. Sangroungrai, S., Sukchareonpong, P., and Witchakul, S. (2018, January 17–18). Engineering, procurement and construction (EPC) project management for reducing cost and time: A case study of petrochemical plant. Proceedings of the Conference ICIBR—Smart Technology for Next Generation of Information, Engineering, Business and Social Science, Bangkok, Thailand.10.1109/ICBIR.2018.8391230 ↗
6. Study on Time and Resource Management in Construction Projects Using MS Project
7. Project management in construction using primavera
8. Impact of Engineering Software on Construction Project Management in Bahrain10.4028/www.scientific.net/AMM.501-504.2614 ↗
9. Jarský, Č. (2019). CONTEC. Construction Preparation and Implementation, Akademické Nakladatelství CERM, s.r.o.. Available online: http://www.contec.cz.
10. Organizational culture and business history10.1177/0170840699203001 ↗
11. Howell, G., and Ballard, G. (, January September). Implementing lean construction: Reducing inflow variation. Proceedings of the 2nd Annual Meeting of the International Group for Lean Construction, Santiago, Chile.
12. Reducing variability to improve performance as a lean construction principle
13. Baseline determination in construction labor productivity-loss claim
14. Construction baseline productivity: Theory and practice
15. Exact relations between four definitions of productivity indices and indicators10.1111/j.1467-8586.2010.00378.x ↗
16. Activity analysis for direct-work rate improvement in construction
17. Połoński, M., and Pruszyński, V. (2020, December 10). The Time Buffers Location and Critical Chain Concepts in Civil Engineering Network Schedule. Part I, Theoretical Background, Przegląd Budowlany. Available online: https://bibliotekanauki.pl.
18. Goldratt, E.M. (1997). Critical Chain, The North River Press.
19. An investigation into the fundamentals of critical chain project scheduling
20. Assessment of labor productivity in construction projects using system dynamic approach
21. Factors Affecting Construction Labor Productivity: Iran Case Study
22. Statistical methods for construction delay analysis10.9790/1684-0925862 ↗
23. Predicting likelihood of cost overrun in educational projects10.1108/ECAM-06-2015-0103 ↗
24. Narbaev, T., and De Marco, A. (2011, January 16–18). Cost Estimate at Completion Methods in Construction Projects. Proceedings of the 2011 2nd ICCPM, IPEDR, Singapore.
25. Application of the EVM method and its extensions in the implementation of construction objects
26. Statistical Analysis of Construction Productivity for Highway Pavement Operations10.1007/s12205-014-0425-2 ↗
27. Using Weibull Analysis for Evaluation of Cost and Schedule Performance
28. Project Performance Evaluation Based on Statistical Process Control Techniques
29. Statistical Process Control of Project Performance
30. Wang, Q., Jiang, N., Gou, L., Che, M., and Zhang, R. (2006, January 21). Practical Experiences of Cost/Schedule Measure through Earned Value Management and Statistical Process Control. Proceedings of the Procedure of International Workshop on Software Process Simulation and Modeling, SPW 20, Shanghai, China.10.1007/11754305_38 ↗
31. Prediction of Project Outcome: The Application of Statistical Methods to Earned Value Management and Earned Schedule Performance Indexes
32. A simulation and evaluation of earned value metrics to forecast the project duration
33. Probabilistic Forecasting of Project Duration Using Kalman Filter and the Earned Value Method
34. Analysis of the Earned Value Management and Earned Schedule Techniques in Complex Hydroelectric Power Production Projects: Cost and Time Forecast
35. Probabilistic Forecasting of Project Performance Using Stochastic S Curves
36. Druker, E., Demangos, D., and Coleman, R. (2009, January 2–5). Performing Statistical Analysis on Earned Value Data. Proceedings of the SCEA/ISPA Conference and Training Workshop, St. Louis, MO, USA. Available online: http://www.iceaaonline.com/ready/wp-content/uploads/2017/09/EV004A-Druker.pdf.
37. Earned Value Management and Risk Management: A Practical Synergy
38. Forecasting schedule reliability using the reliability of agents’ promises
39. Statistical Analysis of delays factors in Construction Projects
40. A Reliability Measure for Time Series Forecasting Predictor10.1016/j.ifacol.2015.05.078 ↗
41. Predicting Cost Overrun in construction Projects
42. Critical factors affecting cost performance: A case of Ethiopian public construction projects
43. Magnitude of Construction Cost and Schedule Overruns in Public Work Projects10.1155/2013/935978 ↗
44. Tommelein, I.D. (1997, January 16–17). Discrete-Event Simulation of Lean Construction Processes. Proceedings of the Fifth Conference of the International Group for Lean Construction, Gold Coast, Australia.
45. System dynamics modeling of design and build construction projects10.1108/14714170210814801 ↗
46. Agent based modeling: A tool for construction engineering and management?10.4067/S0718-50732020000200111 ↗
47. Raoufi, M., Seresht, N.G., Siraj, N.B., and Fayek, A.R. (2018). Fuzzy Simulation Techniques in Construction Engineering and Management. Fuzzy Hybrid Computing in CEM, Emerald Publishing Limited.10.1108/978-1-78743-868-220181004 ↗
48. Fayek, A., Seresht, N.G., and Raoufi, M. (November, January 31). Overview of fuzzy simulation techniques in construction engineering and management. Proceedings of the 2016 Annual Conference of the North American Fuzzy Information Processing Society (NAFIPS), El Paso, TX, USA.
49. Development of the construction scheduling based on fuzzy discrete event simulation for a TFT-LCD plant10.1016/j.promfg.2020.01.201 ↗
50. Application of Fuzzy Logic to Simulation for Construction Operations
51. Application of Modified Earned Value Method for Assessing the Risk and Progress of Construction, Projects
52. Minasowicz, A., Kostrzewa, B., and Zawistowski, J. (July, January 29). Construction project risk control based on expertise using fuzzy set theory. Proceedings of the 28th ISR in Construction, ISARC, Seoul, Korea.
53. Plybankiewicz, E. (2018). Model of Predicting Cost Overrun in Construction Projects. Sustainability, 10.10.3390/su10124387 ↗
54. Modeling schedule overrun and cost escalation percentages of highway projects using fuzzy approach10.1108/ECAM-03-2016-0084 ↗
55. A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
56. Construction project cash flow planning using the pareto optimality efficiency network model10.3846/13923730.2011.604537 ↗
57. Integration of task networks and cognitive user models using coloured Petri nets and its application to job design for safety and productivity10.1007/s10111-005-0010-z ↗
58. Application of extended stochastic Petri nets to simulation and modelling of construction system10.1080/02630259808970227 ↗
59. Sears Petri Nets for Simulation and Modeling of Construction Systems10.1061/(ASCE)0733-9364(1997)123:2(105) ↗
60. A Timed Petri Nets Model for Intermodal Freight Transport Terminals10.3182/20140514-3-FR-4046.00038 ↗
61. Cavone, G., Dotoli, M., and Seatzu, C. (June, January 30). Resource planning of intermodal terminals using timed Petri nets. Proceedings of the 13th International Workshop on Descreet Event, Xi’an, China.
62. Implementation of Construction Performance Database Prototype for Curtain Wall Operation in High-Rise Building Construction10.3130/jaabe.13.149 ↗
63. Quantitative Comparisons of Construction Productivity of Curtain Wall Operations in High-Rise Buildings by Means of Simulation Techniques10.4028/www.scientific.net/AMR.250-253.3577 ↗
64. Partial Simulation Model (PSM) Development for Productivity Analysis on Curtain Wall Operations in High-Rise Buildings10.4028/www.scientific.net/AMM.174-177.1942 ↗
65. Montaser, A., Bakry, I., Alshibani, A., and Moselhi, O. (2011, January 14–17). Estimating Productivity of Earthmoving Operations Using Spatial Technologies. Proceedings of the 3rd International/9th Construction Specialty Conference, Otawa, ON, Canada. Available online: https://www.researchgate.net/publication/281294381.
66. Development of Construction performance Monitoring Methodology using Bayesian Probabilistic Approach
67. Probability forecasting of project duration using Bayesian inference and beta distribution
68. A probabilistic framework for Bayesian adaptive forecasting of project progress10.1111/j.1467-8667.2007.00478.x ↗
69. Application of Bayesian updating for real-time schedule estimation in a concreting operat
70. Statistical methods applied to construction process management
71. Halpin, W., and Han, S. (2005, January 4). The use of simulation for productivity estimation based on multiple regression analysis. Proceedings of the 37th Conference on Winter simulation, Orlando, FL, USA.
72. Productivity Analysis of Building Construction Using Mivan Formwork
73. Factors influencing formwork productivity10.1139/l93-015 ↗
74. A study on productivity of concreting work in building construction in Bengaluru city
75. Forsythe, P.J. (2014, January 21–22). The Productivity of Steel Reinforcement Placement in Australian Construction. Proceedings of the ICEC IX World Congress, Milano, Italy.
76. The Effects of Buildability Factors on Rebar Fixing Labor Productivity of Beamless Slabs
77. A Study of Labor Productivity and Work-Hour Loss—Case Study for Brick Masonry
78. Laborer’s Efficiency of Gypsum Plastering in Sulaimani City’s Projects
79. Monkaew, S., and Nawalerspunya, T. (2022, March 23). A Productivity Rate in Concrete Plastering of Exterior Brick Wall. Intellectual Repository at Rajamangala University of Technology Phra Nakhon, January. Available online: https://repository.rmutp.ac.th/handle/123456789/3118.
80. A Strategy for labor performance improvement for floor tiling work in single storey
81. Novák, M. (2021, March 20). Building, s.r.o. Peckova 13, Prague 8, 186 00. Constr. Implement. Doc., Residential Project Klementova Street Praag 13. Available online: https://uloz.to/file/vpzL0MwviVxc/finep-j1234-zip.
82. Briš, R., and Litschmannová, M. (2022, March 05). Statistics II., VŠB TU Ostrava, CZ.O4.01.3/3.2.15.2/0326. Available online: https://katalog.vsb.cz/documents/95035.
83. Litschmannová, M. (2022, March 05). Pravděpodobnost a Statistika, (Probability and Statistics) Formulas Table. Available online: https://homel.vsb.cz/.../Vzorce-a-tabulky.new.