An Integrated Optimization Method for Resource-Constrained Schedule Compression Under Uncertainty in Construction Projects
Source abstract
Abstract
An integrated solution that considers the shortening of scheduling and the planning of resource integration was conceived. The proposed method allocates the resources and the execution mode costs effectively in order to minimize the project duration and the cost of construction activities. Costs are managed based on the management of the costs already in place for people and those costs involved in the modes of execution of the project, trying to decrease the cost as much as possible. The proposed method is used in order to achieve the maximum potential and minimum costs during a project, including direct costs, indirect costs, and delay penalties. Furthermore, it finds a balance between the costs of acquiring and releasing human resources. The most interesting aspect of the proposed method is that it suggests addressing problems with resource planning and project scheduling simultaneously under uncertainty. FS theory is used to model project activity duration and cost uncertainty in the method. In addition, the above approach involves a genetic algorithm (GA) for schedule optimization. The optimization method utilizes a GA as an optimization approach to identify a set of non-dominated solutions. In this paper, we discuss how string-based multi-object optimization can be solved with ES using the elitist non-dominated sorting genetic algorithm (NSGA-II). The method is implemented in Python (v3.12.9), the computer programming language, as a standalone automated computational tool for schedule optimization in order to subsequently reschedule.
Source: crossref · Quality: baseline
Research context
OpenAlex topics: Resource-Constrained Project Scheduling · BIM and Construction Integration · Scheduling and Optimization Algorithms
SciVX discovery tags are terminology-based. OpenAlex topics are source-provided classifications.
Affiliations
Research Unit of Mechanics, Modeling and Production (U2MP), Department of Mechanical Engineering, National School of Engineers of Sfax (ENIS), University of Sfax, BP 1173—Route de Soukra, Sfax 3038, Tunisia
References (63)
Show source-provided references
1. Factors Affecting Construction Cost in Mara Large Construction Project: Perspective of Project Management Consultant
2. Project schedule compression: A multi-objective methodology10.1108/CI-03-2011-0010 ↗
3. Resource Management in Construction10.1061/(ASCE)0733-9364(1986)112:3(346) ↗
4. Stochastic Time–Cost Optimization Model Incorporating Fuzzy Sets Theory and Nonreplaceable Front10.1061/(ASCE)0733-9364(2005)131:2(176) ↗
5. An Algorithm for Optimal Project Scheduling under Multiple Resource Constraints10.1287/mnsc.17.12.B803 ↗
6. Project scheduling with resource constraints: A branch and bound approach10.1016/0377-2217(87)90240-2 ↗
7. Applying Pareto Ranking and Niche Formation to Genetic Algorithm-Based Multiobjective Time–Cost Optimization10.1061/(ASCE)0733-9364(2005)131:1(81) ↗
8. Kaiafa, S., and Chassiakos, A.P. (2015). A Genetic Algorithm for Optimal Resource-driven Project Scheduling. Procedia Engineering, Elsevier Ltd.10.1016/j.proeng.2015.10.087 ↗
9. Schedule Compression Using Fuzzy Set Theory and Contractors Judgment
10. Using Genetic Algorithms to Solve Construction Time-Cost Trade-Off Problems10.1061/(ASCE)0887-3801(1997)11:3(184) ↗
11. Applying a Genetic Algorithm-Based Multiobjective Approach for Time-Cost Optimization10.1061/(ASCE)0733-9364(2004)130:2(168) ↗
12. Nondominated Archiving Multicolony Ant Algorithm in Time-Cost Trade-Off Optimization10.1061/(ASCE)0733-9364(2009)135:7(668) ↗
13. Discrete particle swarm optimization method for the large-scale discrete time-cost trade-off problem10.1016/j.eswa.2015.12.041 ↗
14. Time-Cost Trade-off Optimization of Construction Projects using Teaching Learning Based Optimization10.1007/s12205-018-1670-6 ↗
15. A survey of variants and extensions of the resource-constrained project scheduling problem10.1016/j.ejor.2009.11.005 ↗
16. Resource-Constrained Project Scheduling: Notation, Classification, Models, and Methods10.1016/S0377-2217(98)00204-5 ↗
17. System reliability theory based multiple-objective optimization model for construction projects10.1016/j.autcon.2012.11.040 ↗
18. Resource-constrained project scheduling: A heuristic for the multi-mode case10.1007/PL00013354 ↗
19. Multimode Resource-Constrained Scheduling and Leveling for Practical-Size Projects10.1061/(ASCE)ME.1943-5479.0000338 ↗
20. A two-phase GA model for resource-constrained project scheduling10.1016/j.autcon.2008.11.003 ↗
21. Multi-objective multi-mode resource constrained project scheduling problem using Pareto-based algorithms10.1007/s00607-018-00693-1 ↗
22. Two Approaches to Problems of Resource Allocation among Project Activities—A Comparative Study
23. Ant colony optimization-based multi-mode scheduling under renewable and nonrenewable resource constraints10.1016/j.autcon.2013.05.030 ↗
24. A resource constrained project scheduling problem with multi-modes
25. Robust optimization for the resource-constrained multi-project scheduling problem with uncertain activity durations
26. Fuzzy-based MOGA approach to stochastic time-cost trade-off problem10.1016/j.autcon.2009.02.001 ↗
27. Stochastic Time-Cost-Resource Utilization Optimization Using Nondominated Sorting Genetic Algorithm and Discrete Fuzzy Sets10.1061/(ASCE)CO.1943-7862.0000092 ↗
28. Stochastic time-cost optimization using non-dominated archiving ant colony approach10.1016/j.autcon.2011.05.003 ↗
29. Fuzzy resource-constrained project scheduling wwe ith multiple routes: A heuristic solution10.1016/j.autcon.2018.11.029 ↗
30. Multi-objective optimization for repetitive scheduling under uncertainty10.1108/ECAM-05-2018-0217 ↗
31. GA-Based Multicriteria Optimal Model for Construction Scheduling10.1061/(ASCE)0733-9364(1999)125:6(420) ↗
32. Multi-mode resource-constrained discrete time-cost-resource optimization in project scheduling using non-dominated sorting genetic algorithm10.1016/j.autcon.2012.11.014 ↗
33. König, M., and Beißert, U. (2009, January 24–27). Construction Scheduling Optimization by Simulated Annealing. Proceedings of the 26th International Symposium on Automation and Robotics in Construction, Austin, TX, USA.10.22260/ISARC2009/0027 ↗
34. Cost Optimization Model for the Multiresource Leveling Problem with Allowed Activity Splitting10.1061/(ASCE)CO.1943-7862.0000251 ↗
35. Resource-constrained project scheduling problem with uncertain durations and renewable resources10.1007/s13042-015-0444-4 ↗
36. Multi-project Time-cost Optimization in Critical Chain with Resource Constraints10.1007/s12205-017-0691-x ↗
37. Integrated time–cost tradeoff and resources leveling problems with allowed activity splitting10.1111/itor.12329 ↗
38. A mixed-integer linear programming model for solving fuzzy stochastic resource constrained project scheduling problem
39. A multi-objective optimization approach to project scheduling with resiliency criteria under uncertain activity duration10.1007/s10479-019-03375-z ↗
40. A new combination of multi-mode resource-constrained project scheduling and group decision-making process with interval-fuzzy information
41. Pisello, A.L., Hawkes, D., Bougdah, H., Rosso, F., Mohareb, N., Mesbah, S., and Mannan, M.A. (2025, March 20). IEREK Interdisciplinary Series for Sustainable Development Editorial Board. September 2020. [Online]. Available online: http://www.springer.com/series/15883.
42. An evolutionary approach for resource constrained project scheduling with uncertain changes10.1016/j.cor.2020.105104 ↗
43. Multi-mode resource-constrained project scheduling with uncertain activity cost10.1016/j.eswa.2020.114475 ↗
44. Project scheduling and material ordering problem with storage space constraints10.1016/j.autcon.2021.103796 ↗
45. A Heuristic-Based Genetic Algorithm for Scheduling of Multiple Projects Subjected to Resource Constraints and Environmental Responsibility Commitments10.1007/s41660-020-00150-7 ↗
46. Improving materials logistics plan in road construction projects using discrete event simulation10.1108/ECAM-08-2018-0317 ↗
47. Rashid, K.M., and Louis, J. (2022). Integrating Process Mining with Discrete-Event Simulation for Dynamic Productivity Estimation in Heavy Civil Construction Operations. Algorithms, 15.10.3390/a15050173 ↗
48. Multimode time-cost-robustness trade-off project scheduling problem under uncertainty10.1007/s10878-020-00636-7 ↗
49. A Robust Bi-objective Optimization Model for Resource Levelling Project Scheduling Problem with Discounted Cash Flows10.1007/s12205-022-0679-z ↗
50. Ghoroqi, M., Ghoddousi, P., Makui, A., Javid, A.A.S., and Talebi, S. (2023). An Integrated Model for Multi-Mode Resource-Constrained Multi-Project Scheduling Problems Considering Supply Management with Sustainable Approach in the Construction Industry under Uncertainty Using Evidence Theory and Optimization Algorithms. Buildings, 13.10.3390/buildings13082023 ↗
51. Optimization of Multi-Execution Modes and Multi-Resource-Constrained Offshore Equipment Project Scheduling Based on a Hybrid Genetic Algorithm
52. Zohrehvandi, M., Zohrehvandi, S., Khalilzadeh, M., Amiri, M., Jolai, F., Zavadskas, E.K., and Antucheviciene, J. (2024). A Multi-Objective Mathematical Programming Model for Project-Scheduling Optimization Considering Customer Satisfaction in Construction Projects. Mathematics, 12.10.3390/math12020211 ↗
53. Lazari, V., Chassiakos, A., and Karatzas, S. (2024). Multi-Objective Resource-Constrained Scheduling in Large and Repetitive Construction Projects. Algorithms, 17.10.3390/a17080351 ↗
54. Preemptive and non-preemptive multi-skill multi-mode resource-constrained project scheduling problems considering sustainability and energy consumption: A comprehensive mathematical model10.1016/j.jenvman.2024.121986 ↗
55. Hybrid differential evolution algorithm for the resource constrained project scheduling problem with a flexible project structure and consumption and production of resources10.1016/j.ejor.2023.07.043 ↗
56. Mohammadjafari, A., Ghannadpour, S.F., Bagherpour, M., and Zandieh, F. (2025). Multi-Objective Multi-mode Time-Cost Tradeoff modeling in Construction Projects Considering Productivity Improvement. arXiv.
57. Wang, H., and Gao, F. (2024). Research on project schedule optimization model construction and engineering efficiency improvement method. Appl. Math. Nonlinear Sci., 9.10.2478/amns-2024-2554 ↗
58. Fixed start method for repetitive project scheduling with simulated annealing10.1016/j.heliyon.2025.e41741 ↗
59. Constructing fuzzy measures in expert systems10.1016/S0165-0114(97)00174-7 ↗
60. Transit search: An optimization algorithm based on exoplanet exploration10.1016/j.rico.2022.100127 ↗
61. Multi-Objective Optimization Model for Inspection Scheduling of Sewer Pipelines10.1061/(ASCE)CO.1943-7862.0001599 ↗
62. A comprehensive study on modern optimization techniques for engineering applications10.1007/s10462-024-10829-9 ↗
63. A multi-objective invasive weed optimization method for segmentation of distress images10.32604/iasc.2020.010100 ↗